https://planningdocuments.warwickdc.gov.uk/online-applications/applicationDetails.do?activeTab=summary&keyVal=_WARWI_DCAPR_80173


Click on the Link above

To view plans and proposals for your new Village Hall, which were approved by Warwick Planning Committee on 10th October 2018, note there are later amendments.

The report with conditions is available to read. This will allow the Trustees to plan construction, starting with Building Regulations,and publish the anticipated completion date.

1st Phase Village Hall Site

Enabling works June - October 2019

The diversion of the fuel pipeline has now started which will be followed by the construction period diversion of the Greenway.

It is anticipated that the diverted Greenway will be available to the public by the end of the year. At that time the construction of the New Village Hall hopefully will have started.

Haul routes will be created along the line of the proposed railway to facilitate removal of spoil when excavating the

“Green Tunnel”