  Burton Green

    Village Hall


https://planningdocuments.warwickdc.gov.uk/online-applications/applicationDetails.do?activeTab=summary&keyVal=_WARWI_DCAPR_80173


Click on the Link above

To view plans and proposals for your new Village Hall, which were approved by Warwick Planning Committee on 10th October 2018, note that there are later amendments.

1st Phase Village Hall Site

Enabling works June - March 2021

The diversion of the fuel pipeline is now complete and the site passes to LM who are contracted to build the diverted Greenway along with other enabling work for HS2.

We anticipate that we will bring archaeologists and surveyors on site to be prepared for our construction start.

 The construction of the New Village Hall will start following the appointment of a Contractor, hopefully the early 2021. Aiming to complete the building by Easter 2022

Haul routes will be created along the line of the proposed railway to facilitate removal of spoil when excavating the

“Green Tunnel”